Introduction
I undertook a complete renovation of a small bathroom in my apartment. I bought this apartment in 2018, but it was built in 2008. The goal was to modernize the space with a minimalist design while optimizing the use of available space, and especially to get rid of the ugly original orange and green tiles.
3D Project
Before starting the work, I used the Home by Me application to create 3D visualizations of the project. These renderings allowed me to validate the design and equipment layout before starting demolition.
The project planned for a modern bathroom with an integrated laundry area, a vanity unit, and a bathtub with shower. The design favored light tones (white and light grey) with touches of natural wood to bring warmth to the space.


Demolition
The first step was to demolish the existing elements. I removed the old tiles, finishes, and exposed the walls to assess the structure's condition and prepare for new installations.

Plumbing Work
Once demolition was complete, I proceeded with installing the new plumbing. I replaced the old pipes with copper pipes for hot and cold water supply, and PVC pipes for drainage.
Installing the bathtub required particular attention to ensure proper connection to water and drainage networks.


Electrical and Structural Work
I installed a metal frame to create a soffit above the vanity unit, which will house the recessed LED spotlights. This structure also allows hiding ventilation and electrical conduits.

Ventilation Installation
Installing an efficient ventilation system is essential in a bathroom. I set up a ventilation duct in the opening framed by the metal structure.

Partition Wall Construction
To optimize space, I built a partition wall. The partition was made with moisture-resistant drywall panels.

Tiling
Tiling was done with white rectangular tiles laid in a staggered brick pattern. I used a laser level to ensure perfect tile alignment and spacers to maintain regular joints.
The work was done in several stages, starting with the walls behind the vanity unit and bathtub.



Finishing Installation
Once tiling was complete, I installed the finishing touches: mirror with light wood frame, shower curtain with geometric pattern, and OSB side panels for the bathtub.
Final Result
The renovation is now complete. The bathroom features a modern and minimalist design with dark grey side panels for the bathtub, completed white tiling, a mirror with wood frame, and all equipment in place. The soffit with its recessed LED spotlights provides modern and functional lighting.